April 20, Fuan Tsingtuo stainless steel plate project site a hot construction scene. At present, the project has completed 98% of the plant building, 98% of the equipment foundation has been completed, the equipment is stepping up the installation, is expected to be the end of June or early July trial production, than the original plan ahead of 2 to 3 months.
According to reports, the project investment of 3.5 billion yuan, mainly the construction of a stainless steel 3500 mm medium-thick plate hot rolling production line, with an annual output of 1 million tons of medium-thick plate stainless steel, 2025 is expected to invest an amount of 1.5 billion yuan, full production can be realized after the annual output value of more than 12 billion yuan, and it is expected that the new jobs 800. The products produced by the project will fill the gaps of conventional medium-thickness plate mill products to meet the needs of special industries and special users.
Questions? Contact us Anytime! Fill out the form below with as much information as possible and we will get back to you quickly!